with a clear SOW a contractor completes work as sp

计算机考试 已帮助: 时间:2025-02-02 00:20:04

with a clear SOW a contractor completes work as specified,but the buyer is not pleased with the result.the contract is considered to be ( )
A.incomplete because the buyer is not pleased
B.incomplete because the specs are incorrect
C.compete because the contractor meets the terms and conditions of the contract
D.complete because the contractor is satisfied
请帮忙给出正确答案和分析,谢谢!

难度:⭐⭐⭐

题库:计算机类考试,软考(中级),中西医结合助理医

标签:正确答案,请帮忙,buyer

参考解答

用户头像

406***114

2025-02-02 00:20:04

正确答案:C
有一个清晰的工作说明书,且承包商完成了指定工作,但买方不满意结果。合同被认为是(75)。A.未完成,由于买方不高兴B.未完成因为规格是不正确的C.完成了,因为承包商符合合同的条款和条件D.完成了,因为承包商是满意的

上一篇 A. extending B. minimizing C. demolishing D. reduc

下一篇 在下列常见的软件开发模型中 主要用于描述面向对象的开发过程的是( 19)。A.瀑布模型 B.演化模型